In stressing a double live- end anchorage where the other end is a pan box type. What is the stressing sequence inorder to achieve optimum elongation?
Basing from experience, the best way to stress a double live-end anchoragewhere the other side is a pan box anchorage is to do initial stressing at the pan box end, then on final stressing stage complete 100% stressing at the edge slab end.Then do the “pick-up” at the pan box end.This process may minimize the friction losses at the pan box end.
I call it box-out, but we are on the same page
I agree with your sequence of stressing- at box initial-final-pick-up at box
Stressing from box-out we use bending device looks like two or three pcs connected together providing necessary angle
this small device create huge friction just infront of the jack, area between the arrows on my sketch
and ofcourse this affects stressing.
Thank you
And What Friction!
Hope the designers leaves you withs some capacity to overcome it 